A two-mile
stretch of road in eastern Independence could pave the way
for thousands of new homes and a stronger road network
linking with Blue Springs.
When
completed, the 39th Street realignment project will result
in a four-lane road beginning just east of the Little Blue
River, cutting straight across 1,000 to 2,000 acres of
undeveloped land, and ending at R.D. Mize Road.
The
39th Street Transportation
Development District is financing the project
with a one-eighth-cent sales tax on businesses along 39th
Street.
“The
pavement and storm-sewer connections along the extension are
basically completed,” said Shar Dilmaghani, construction
projects manager for the
Independence Public Works
Department. “The 150 feet at the two ends of the
project that tie into R.D. Mize Road and 39th Street is not
in yet.”
|